| 30th January 2003 We started work on our new extension on January 20th and we hope that the building will be completed by the end of July. The equipment will be installed from May onwards and we hope that it will be working at the end of August, with commercial production beginning a little later.First comes the demolition of the old Loading Bay and "Foreign" Beer store (Lagers and Stouts for our Tied Estate). Afterwards we shall excavate the area to be developed and then the building will start in earnest. Here are the pictures after the first week of demolition. There are more to come in the following weeks. |
||
| The Way We Were | |
![]() |
![]() |
| 14th February 2003 The piling has been done to underpin the foundations that will be built over the next three weeks. Over 40 columns were put in as shown in the pictures. The Piles are driven from the ground surface to the bedrock: up to 11 metres in depth. We are indebted to our Structural Engineer Paul Hutchinson (of the Hutchinson - Whitlam Partnership in Ilkley) for his calculations which led to the piling being efficiently carried out.The next few weeks will see further excavation and foundation work. Accordingly, the Progress of The Brewery Expansion will continue when Walls and Girder Work are begun in about a month's time. |
||
| 28th March 2003 The Foundations have now been completed by our Main Contractor R.N. Wooler & Co.of Keighley. Next week sees the arrival and erection of the steel girders which will support the new building. |
||
| 4th April 2003 What a difference a week makes! Girder Work for the Structure of the new Building has been erected this week. You can now see the outline of the Extension. The work was carried out under Hambledon's Steel of Richmond, Yorkshire. Next Week will see the Girders accurately aligned and blockwork begin. |
|
|
| Week 15 May 2nd The Blockwork has been done on the top floor. Here will
go the New Fermenters in the middle of May. Everything is ready now for
the Cladding which will take place before then.. |
|
|
| Week 19 - 30th May: Now that the Fermenters have been installed, the Cladders
and Roofers can work on the outside of the frame of the building. |
Click to enlarge |
|
| Week 24 - July 4th. The Cladding has been completed and the Building is all
but finished. The Principal Contractor Norman Wooler (R.N. Wooler Ltd.
of Keighley) is ready to hand over the project to the Engineers who have
been appointed to manufacture & install the equipment. The scheduled
date for the first pieces of machinery to arrive was 7th July, so the
Building is ready just in time! |
Click to enlarge |
|
| Week 25 - July 11th. The first parts of the machinery are delivered
- the Frame for the Racking (Cask Filling) Machine and Turners to "upend"
the Casks. |
Click to enlarge |
|
| Week 28 - August 1st . The Building is complete and our thanks go to the following:
from left to right - Paul Hutchinson (Structural Engineer), Mike Regan
(Architect), Dave Kettlewell (Woolers - The Principal Contractor) |
Click to enlarge
|
|
| Week 33 - September 5th The Cask Filling Machine, Conveyors, Tanks and Pipework
have been assembled. The Filling Machine or Racker by Esau Heuber, the
Conveyors by Microdat and the Pipes and Tanks by Bibby's. It is now time
to connect the electronic wizardry that will operate the machinery |
Click to enlarge |
|
Week 52 - January 5th 2004 After a year the whole New Development has been completed.
The New Fermenting Tanks have been working since August 2003. The New
Cask Filler (Racker) and New Warehouse have been in constant use since
November 2003. The Palletiser and The New Labeller/Bung Presser were working
just before Christmas. These new pieces of equipment will help us at Taylor's
brew and distribute our beer efficiently and hygienically for the future.
A big thank you comes from us to all the Builders, Engineers and Contractors
who supported us through this huge and complex project. |
|
The Filling Machine, The New Labeller and Bung Presser |
The Palletiser and The Flexitruck in The New Warehouse. |